Product description
This device is a special supporting equipment for accelerated
cooling with compressed air after the large-capacity turbine is
shut down. It uses compressed air to accelerate the shutdown of the
steam turbine. After the cooling system is equipped with this
device, the initial temperature of the cooling medium-air can be
based on the metal temperature level during the shutdown and the
different cooling stages in the entire cooling process. Temperature
difference and cooling speed can be easily adjusted.
Product Features
It is a new type of air purification device which is based on
aerosol mechanics and condensed filtration mechanism to remove dust
from compressed air. Oil mist The filtration efficiency of wet
purification is less than 99%. Gu Ke desiccated the steam turbine
when it was fast cooling. Clean air quality,characteristics of
electric heaters;Compressed air electric heaters are made up of
multiple heating tubes. Cylinder body Spiral diversion baffle and
so on.
The equipment adopts two high-efficiency deoiling filters, which
are separated by centrifugation, followed by stainless steel wire
mesh, and then through filters with special ultra-fine fibers as
the main body.
The heater core takes the form of spiral diversion, and compressed
air enters the heater interior for heating. The heater core is
heated by rotating flow around the heater core, and each heating
part of the heater element can be effectively utilized. The heat
transfer effect of the heat pipe is effective.
The heating wire, magnesia powder and other materials of electric
heater are made of high quality materials from selected import,
which enhance the service life of heating pipe.
Specifications
Model | Power (KW) | Working Pressure (Mpa) | Working Temperature (℃) | Working Flow (m³/min) |
GAO-13 | 75 | 0.8 | 350 | 15 |
GAO-20 | 150 | 0.8 | 350 | 20 |
GAO-30 | 200 | 0.8 | 350 | 30 |
GAO-33 | 250 | 0.8 | 350 | 30 |
GAO-50 | 250 | 0.8 | 350 | 35 |
GAO-60 | 250 | 0.8 | 350 | 40 |
GAO-100 | 300 | 0.8 | 350 | 60 |
Preparation before commision
rapid cooling equipment debugging personnel clear division of
labor, on-site control of one person, valve opening two,
centralized control room to monitor one person, to maintain smooth
communication, timely follow the commander's orders.
the operator of the control cabinet shall be responsible for all
the functions of the screen, buttons, switches, system settings,
etc., to be understood, proficient, and skilled in the operation of
the professional personnel, (see the control panel diagram for more
details)
the unit is ready to use the quick cooling device after shutdown,
the sliding parameter should be used as far as possible, and the
temperature after shutdown should be reduced as much as possible.
The first stage metal temperature of the high pressure cylinder and
the inlet blade ring temperature of the middle pressure cylinder
drop below 400 ℃.
before forced ventilation and cooling, steam turbine high, medium
pressure cylinder should be fully drained and completely isolated.
Because the drainage discharge is not enough or the system is not
strictly isolated, the cold steam and cold water enter into high,
the local temperature difference in the middle pressure cylinder is
too large, and the temperature drop rate is too large.
Attention Please in coolong process
The absolute expansion, expansion difference, rotor eccentricity,
axial displacement and so on should be monitored in the whole
process of forced ventilation and cooling.
After putting the steam turbine into quick cooling, it is just
beginning to supply gas, adopting small temperature difference and
small flow rate as far as possible, then gradually increasing the
flow rate, strictly controlling the intake temperature and
ventilation volume of the cylinder
In principle every adjustment, stable for 30 minutes, no change or
little change, adjust again.
Air heater outlet temperature should be steadily reduced without
sudden jump phenomenon, when high, medium pressure cylinder inlet
air diversion pipe wall temperature of 100; When the first metal
temperature of the high pressure cylinder falls below 200 ℃, the
ventilation volume can be increased, the fully open electric
regulating valve and the full open high, medium pressure cylinder
inlet valve can be increased when the temperature is about 200 ℃.
When the first stage metal wall temperature of the high pressure
cylinder and the ring holding temperature of the first static blade
of the middle pressure cylinder are below 150 ℃, there is no
obvious increase, and the forced ventilation cooling is finished.
Close the high, medium pressure cylinder intake valve, and then
continue to turn the car for 30 minutes, depending on whether the
temperature pick-up or not, if not, can stop the car, start
maintenance work.
After all the operation, close the compressed air manual valve and
electric regulating valve, open the quick cooling device sewage
valve, turn off the power supply, check the equipment for abnormal
conditions,facilitate the next normal operation.